Free 70-466 Braindumps

A. Modify the Rsmgrpolicy.config file.
B. From Central Administration, modify the SMTP settings of the SharePoint Server server farm.
C. Modify the Rssrvrpolicy.config file.
D. From Central Administration, modify the properties of the Reporting Service Application.

Answer(s): B

QUESTION:
3
You need to modify the environment before you create the QuarterSales report.
What should you do?

A. Add a date table to the model that contains columns for the fiscal and calendar quarters.
B. Add a date table to the model that contains measures for the fiscal and calendar quarters.
C. Configure a time dimension by using the Time Intelligence Wizard.
D. Configure SSAS to use a server time dimension.

Answer(s): C

QUESTION:
4
You need to configure the dataset for the ManufacturingIssues report. The solution must meet
the technical requirements and the reporting requirements.
What should you do?

A. Configure the dataset to use a stored procedure. Add the necessary parameters to the stored
procedure.
B. Add a query to retrieve the necessary data from the database. Configure the dataset to use
query parameters.
C. Add a query to retrieve the necessary data from the database. Configure the dataset to use
filter parameters.
D. Configure the dataset to use a table. Ensure that the database has a table that contains the
necessary information.

Answer(s): B

QUESTION:
5
You need to ensure that all reports meet the reporting requirements.
What is the best way to achieve the goal? More than one answer choice may achieve the goal.
Select the BEST answer.

A. Create a report part. Publish the report part to a server that has SSRS installed. Add the
report part to each new report that is created.
B. Create a report part. Publish the report part to a SharePoint site. Add the report part to each
new report that is created.
C. Create a report. Copy the report to source code control. Create each new report by using the
report template in source code control.
D. Create a report. Copy the report to the PrivateAssemblies\ProjectItems\ReportProject folder
in the Visual Studio directory. Create each new report by using the local y stored report
https://xcerts.com