tasks, but you know the resource roles that are necessary. One of the roles needed is
architect.
You need to estimate how many architect hours are required to complete the work.
What should you do?

A. Add a Material Resource named architect.
B. Add a Budget Resource named architect.
C. Add a Work Resource named architect,
D. Add a Cost Resource named architect.
Answer(s): C

QUESTION:
4
Your company uses Project Professional 2013.
You are setting up a preliminary schedule by using manual y scheduled tasks. You create a
task with no duration, start, or finish date, and then you assign a resource. Later, you enter
duration of three days for that task.
You need to let the resource know how the Work will be affected.
What should you say?

A. Work wil increase to 24 hours.
B. Work wil remain at 0 hours.
C. Work wil increase to 16 hours.
D. Work wil remain at 8 hours.
Answer(s): A

QUESTION:
5
You are a program manager who uses Project Professional 2013.
You manage a portfolio of projects for a large point of sale implementation. Al of your project
managers have created individual project schedules. You discover that you have resource
constraints since multiple resources are working on multiple projects.

You need visibility into resources across all projects so that you can most efficiently manage
the resources and their availability.
What should you do?

A. Create a shared resource pool and send the location to each project manager. Open the
individual project and the resource pool. From the individual project, select Resource Pool,
Share Resources, and choose Use Resources.
B. Create a shared resource pool and send the location to each Project Manager. Open the
individual project, select Resource Pool, Share Resources, and choose Use Resources.
C. Create a master resource list and send it to each project manager. Open the individual
project and copy and paste it into the Resource Sheet.
D. Create a master resource list and send it to each project manager. Open the individual
project, select Team Planner, and add the resources.