QUESTION: 1
Select the three statements that are true about the Project management Plan.

A. It is created in the Manage Project Execution and Control phase.
B. It is the single most important work product produced by the project manager.
C. Its main focus is on scheduling the project.
D. It is created by the project manager and the client.
E. It is a conceptual work product comprised of process components detailing the tools
and/or approach for each OUM Manage process.
F. It provides a framework for the Analysis and Design processes.
Answer(s): B, D, F
Explanation:
*In OUM Manage, one of the first activities that occur during the Project Startup phase
involves the Project Manager and the client (Project Sponsor) jointly creating the Project
Management Framework. This framework establishes the ground rules for the project and is
the first step in communicating, establishing trust, and setting expectations.
The key focus for the remainder of the Project Startup Phase is to evolve the Project
Management Framework into a detailed Project Management Plan based on the agreed
upon foundation.
*The project manager creates the project management plan following input from the project
team and key stakeholders. The plan should be agreed and approved by at least the project
team and its key stakeholders.
Incorrect:
Not A:Project Execution and Control runs concurrently with the Implement focus area
phases. The purposeof the Project Execution and Control Phase is to provide adequate
visibility into actual progress so thatmanagement can take effective actions when the
project's performance deviates significantly from theproject plans. The Project Execution and
Control Phase includes tracking and reviewing the projectsaccomplishments and results
against documented WBS, project estimates, time schedule, resourcesplan, and cost
budget, and adjusting these plans based on the actual accomplishment and results.

QUESTION:
2
Select the three constraints that are missing in this Triple Constraint triangle.
A. Usability
B. Scope
C. Cost


2