QUESTION: 1
A contract cannot contain _____________.

A. Il egal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above

Answer(s): A
Explanation:
A contract cannot contain illegal activities. A contract can contain other options available.
QUESTION: 2
Which one of the following comes first in the project plan?

A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan

Answer(s): A
Explanation:
Scope statement comes first in the project plan. Scope statement is the written
statement of project. It contains: Project objectives, Project justification, Project
deliverables
QUESTION: 3
You are project manager of a project. During the process of selecting the sellers, you
reject one vendor because it doesn't have the manufacturing capability. This is an
example of which selection tool?

A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment

Answer(s): B
Explanation:
A screening system rejects sellers that does not meet minimum requirements for the
project.
QUESTION: 4
______________ provides details about how the project scope may be changed.

A. Control Scope system