QUESTION: 23

A project in which the scope, time, and cost of delivery are determined as early as possible
is following a life cycle that is:

A. Adaptive
B. Predictive
C. Incremental
D. Iterative

Answer(s): B
QUESTION: 24

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual
cost (AC) is $150, and the earned value (EV) is $50?

A. 0.50
B. 0.67
C. 1.50
D. 2.00

Answer(s): A
QUESTION: 25

Which item is an input to the Define Activities process?

A. Schedule data
B. Activity list
C. Risk register
D. Scope baseline
Answer(s): D
QUESTION: 26

When alternative dispute resolution (ADR) is necessary, which tool or technique should be
utilized?

A. Interactive communication
B. Claims administration
C. Conflict management
D. Performance reporting

Answer(s): B