Which quality management and control tool is useful in visualizing parent-to-child
relationships in any decomposition hierarchy that uses a systematic set of rules that define a
nesting relationship?

A. Interrelationship digraphs
B. Tree diagram
C. Affinity diagram
D. Network diagram

Answer(s): B
QUESTION: 28

The only Process Group that comprises processes that typically occur from the beginning to
the end of the project life cycle is:

A. Planning.
B. Executing,
C. Monitoring and Controlling.
D. Closing.

Answer(s): C
QUESTION: 29

Organizational theory is a tool used in which Project Human Resource Management
process?

A. Manage Project Team
B. Acquire Project Team
C. Develop Project Team
D. Plan Human Resource Management

Answer(s): D
QUESTION: 30

Which tools or techniques are used in the Plan Schedule Management process?

A. Benchmarking, expert judgment, and analytical techniques
B. Statistical sampling, benchmarking, and meetings
C. Negotiations, pre-assignment, and multi-criteria decision analysis
D. Expert judgment, analytical techniques, and meetings

Answer(s): D
QUESTION: 31

A project manager is appointed full-time to a project and is given full-time administrative staff
and full-time project team members. This situation describes which type of organizational
structure?
8