A. Projectized
B. Weak matrix
C. Functional
D. Balanced matrix

Answer(s): A
QUESTION: 32

A project charter is an output of which Process Group?

A. Executing
B. Planning
C. Initiating
D. Closing

Answer(s): C
QUESTION: 33

Which tool or technique is effective in a project in which the deliverable is not a service or
result?

A. Inspection
B. Variance analysis
C. Decomposition
D. Product analysis

Answer(s): D
QUESTION: 34

An element of the project scope statement is:

A. Acceptance criteria.
B. Astakeholder list.
C. Asummary budget,
D. High-level risks.

Answer(s): A
QUESTION: 35

Which document describes the necessary information to determine if a project is worth the
required investment?

A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case