QUESTION: 36

Which process involves monitoring the status of the project to update the project costs and
managing changes to the cost baseline?

A. Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management

Answer(s): B
QUESTION: 37

Which group is formally chartered and responsible for reviewing, evaluating, approving,
delaying, or rejecting changes to the project and for recording and communicating
decisions?

A. Project team
B. Focus group
C. Change control board
D. Project stakeholders

Answer(s): C
QUESTION: 38

Plan Schedule Management is a process in which Knowledge Area?

A. Project Scope Management
B. Project Human Resource Management
C. Project Integration Management
D. Project Time Management

Answer(s): D
QUESTION: 39

An output of the Validate Scope process is:

A. Arequirements traceability matrix.
B. The scope management plan.
C. Work performance reports.
D. Change requests.

Answer(s): D