QUESTION:
6
Your company uses Project Professional 2013.
You are a program manager in charge of a multi-program software integration project. The
project is scheduled from January 1, 2012-August 3, 2013. You have a consultant resource
that charges a different rate based on each task completed. Tasks 1 through 9 are bil ed at a
rate of $150.00 per hour. Tasks 10 through 20 are bil ed at a rate of $175.00 per hour.
You need to set up your schedule to ensure that the correct resource rate is associated with
the correct tasks.

Which two actions should you perform in sequence? (To answer, move the appropriate two
actions from the list of actions to the answer area and arrange them in the correct order.)

A. The answer is not available.

Answer(s): A

QUESTION:
7
Your organization uses Microsoft Project 2013.
You are finalizing the Project Schedule for a very complex project with over 100 resources.
You need to ensure that all tasks are assigned to resources.
What should you do?

A. Use Task Usage view and look for Unassigned tasks.
B. Use Resource Graph view and look for the Unassigned resource name.
C. Use Resource Usage view and look for the Unassigned resource name.