D. Use Resource Sheet view and look for Unassigned tasks.
F. The answer is not available.

Answer(s): F
QUESTION: 8
You are a project manager who uses Project Professional 2013.
You work on a construction project that requires propane as a fuel source for your
equipment. The foreman requires that you enter project costs associated with all work
completed on your project.
The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time
the tank is refil ed, you must pay a fee of $20.
You need to enter the propane costs into your project schedule prior to fil ing the propane
tank for the first time.
What should you do?

A. Create a material resource with a material label of gallons. Enter $20 in the cost per use
and $5.00 in the standard rate.
B. Create a cost resource, add the resource to a task, and enter $25 in the actual cost.
C. Create a material resource with a material label of gallons. Enter $20 in the standard rate
and $5.00 in the cost per use.
D. Create a cost resource, add the resource to a task, and enter $2520 in the actual cost.
Answer(s): A

QUESTION:
9
You are a project manager for a software development company. You use Project
Professional 2013.
You manage an integration project, and you discover that you need to add additional
resources to the integration tasks in order to meet your development complete milestone
date. The project is behind schedule, so you must shorten the duration of the integration
development work.
You identify two additional resources to work on the integration task. When you add these
resources, your task now shows it wil complete three days ahead of schedule, which leaves
a contingency window for issues that may arise.
In order to shorten the duration of the task when the resources are added, you need to set
the task type before adding the resources.
What should you do?

A. Use an automatically scheduled task and set the task type to fixed duration.
B. Use a manual y scheduled task and set the task type to fixed work.
C. Use an automatically scheduled task and set the task type to fixed work.
D. Use a manual y scheduled task and set the task type to fixed duration.
F. The answer is not available.

Answer(s): F