QUESTION: 10
You are a project manager, and your organization uses Project Professional 2013.
You have created a detailed project schedule and have identified two tasks that are causing
your resource to be overallocated.
You need to use the Team Planner to reassign these tasks from the overallocated resources
to underallocated resources with the same skil set.
What should you do?

A. Right-click the task and reassign it to the underallocated resource.
B. Drag the underallocated resource on the task to reassign it.
C. Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.
D. Right-click the resource and reassign it to the underallocated resource.
Answer(s): A

QUESTION:
11
You are a senior project manager, and your organization uses Project Standard 2013.
You are managing a large ERP project with both part-time and full-time resources. The part-
time resources have strict contractual limitations regarding working days and hourly
availability.
You need to make sure the tasks for your part-time resources are only scheduled in the
calendar during their agreed-upon working days and hours.
What should you do?

A. Change the part-time resources' tasks to manually scheduled to ensure the dates do not
go past the agreed-upon terms of their contract.
B. Enter the availability start and end dates for each resource and change the percent of
units to the agreed-upon amount in their contract.
C. Enter the availability start and end dates for each resource and change the working time
for each resource to only include days and hours agreed upon in their contract.
D. Change the part-time resources' units to the percentage they are available and set task
constraints to must finish on to ensure the dates do not go past the agreed-upon terms of
their contract.
Answer(s): C

QUESTION:
12
Your organization uses Project Professional 2013.
A senior stakeholder in a project asks you to determine when a task is over budget by
comparing the baseline cost of a task to the cost. Additionally, the senior stakeholder wants
you to display a graphic indicator when the baseline cost is greater than the cost.
You write a formula to display the indicator, but it only displays for normal tasks and not for
summary tasks.
You need to make the indicator display for summary tasks.