Free 74-343 Braindumps

8

D. Copy and paste the tasks from SharePoint into Project Professional 2013.
Answer(s): C

QUESTION:
15
You are a project manager who uses Project Standard 2013.
You have been told to build multiple project files for a program.
You need to have all of your projects start with auto scheduled tasks by default.
What should you do?

A. Under schedule options, set New tasks created to Auto Scheduled for each project.
B. Use the Task Mode field to change the first task to Auto Schedule, then copy down for all
of your tasks.
C. Under schedule options, set New tasks created to Auto Scheduled for all new projects.
D. Highlight all of the tasks in your schedule and select the Auto Schedule button.
F. The answer is not available.

Answer(s): F

QUESTION:
16
You are a resource manager who uses Project Standard 2013.
You manage all of your resources in a single plan, which acts as a Shared Resource Pool
for other projects in your organization. Each resource needs to pass an annual exam in
order to work on construction sites.
You need to set up a method that allows you to pick the renewal month for each resource.
What should you do?

A. Rename the Resource Text1 Custom field to Exam Expiration Date. Enter the month
when the exam expires. Select the correct expiration date for each resource.
B. Use the Organizer to copy the Resource Finish1 Custom field from the Global.mpt. Select
the correct expiration date for each resource.
C. Rename the Resource Date1 Custom field to Exam Expiration Date. Create a Lookup
table with values containing the last date of each month. Select the correct expiration date
for each exam.
D. Rename the Resource Month1 Custom field to Exam Expiration Date. Create a Lookup
table with monthly values. Select the correct expiration month for each exam.
E. Rename the Resource Flag1 Custom field to Exam Expired Date. Enter the expiration
dates into a Lookup table. Select the correct expiration date for each resource.
Answer(s): C

QUESTION:
17
You are a project manager who uses Project Professional 2013.
Two of your resources job share; Resource1 works Monday, Tuesday, and a half day
Wednesday. Resource2 works the remaining work week.