How to apply the cadence and synchronization?

  1. Creating cross-functional teams
  2. Conducting the PI Planning Meeting
  3. Allocating budgets to Agile Release Trains
  4. Using the Portfolio Kanban System

Answer(s): B

Explanation:

A PI planning meeting is a cadence-based, face-to-face event that serves as the heartbeat of the ART, aligning all the teams on the ART to a common mission and vision.



What is the team commitment during the PI Planning?

  1. A team commits to the PI Objectives with the highest business value
  2. A team commits to all Stories they put on their PI plan
  3. A team does not commit to stretch Objectives
  4. A team commits to all PI objectives.

Answer(s): C

Explanation:

Objectives are business summaries of what each team intends to deliver in the next PI. During PI planning, Strech Objectives are items which are low in confidence for commitment. Stretch Objectives are not included in Team commitment. According to #3 of SAFe – ” Assume Variability; preserve options we do consider alternatives rather preserving options. All the alternatives of implementation may not be committed. Thus, the scope is split into committed and stretch objectives



What is defining the average lead time in the Cumulative Flow Diagram?

  1. A Measure the horizontal distance between arrival and departure lines on a Cumulative Flow Diagram (CFD)
  2. Measure the vertical distance between arrival and departure lines on a Cumulative Flow Diagram (CFD)

Answer(s): A

Explanation:

The cumulative flow diagram is used to measure the flow of Kanban system. In CFD, The arrival curve shows the rate at which backlog items are pulled into the work. The departure curve shows when they have accepted. The X axis (horizontal distance) shows the average lead time. The vertical line represents the Work in Progress (WIP)



What is true about Strategic Themes?

  1. Strategic Themes are a high-level summary of each program’s Vision
  2. Strategic Themes represents the larger business initiatives that require WSJF prioritization and a lightweight business case
  3. It Links Enterprise Business Strategy with the SAFe portfolio
  4. It allocate budget for Value Streams

Answer(s): C

Explanation:

Strategic Themes connect each SAFe portfolio to the enterprise business strategy. Strategic Themes influence ART funding, Portfolio Backlog, Program Vision, and Roadmap. Strategic Themes represent the key direction for the portfolio. Strategic Themes provides business context for decision-making within the portfolio and influence investments in value Streams and serve as input to the Economic Framework, Budget, Portfolio, Solution, and Program Backlog decisions.



Page 10 of 22



Post your Comments and Discuss Scaled Agile SAFe-Agilist exam with other Community members: