Free Oracle 1Z0-489 Exam Braindumps (page: 3)



Answer(s): B
QUESTION: 8
You power -on PDomain0 and notice that it does not go through POST, Examine the following
output:

In order for this to go through post, which property needs to be changed?

A. level
B. mode
C. power_on_level
D. error_reset_level

Answer(s): C
QUESTION: 9
Which three statements are true about the newest clock board redesign/ operation in a SPARC
M5-32/M6-32 server?

A. There are two clock boards in a redundant configuration, so the failure of the primary clock
boarddoes not cause a reboot of the server.
B. There are two clock boards. Each has two clock sources, so if a clock source fails, the
alternate clock source on the same board takes over.
C. While the system is running on an active clock board, a faulty clock board can be
replaceddynamically.
D. There are two clock boards in a redundant configuration, and there is a dynamic failover of
theprimary clock board to the standby clock board.
Viewing page 3 of 23
Viewing questions 9 - 12 out of 79 questions



Post your Comments and Discuss Oracle 1Z0-489 exam prep with other Community members:

1Z0-489 Exam Discussions & Posts