Free AACE-PSP Exam Braindumps (page: 14)

Page 14 of 31

The linear scheduling velocity diagram has the following two-axis:

  1. Location and crew size
  2. Time and location
  3. Time and rate of progress
  4. Time and crew size

Answer(s): C



Total float is defined as the amount of time an activity can be delayed without impacting

  1. The overall project completion
  2. The buoyancy of a successor activity
  3. The next activity
  4. The end of that activity

Answer(s): A



If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

  1. The Eichleay formula
  2. Historical production rates
  3. Time impact analysis
  4. Black-Scholes model

Answer(s): B



If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

  1. 8 days
  2. 6 days
  3. 4 days
  4. 5 days

Answer(s): B



Page 14 of 31



Post your Comments and Discuss AACE International AACE-PSP exam with other Community members:

Mombasa commented on September 14, 2024
Can you all f***ing b**ches post some helpful comments here or share your experience?
Anonymous
upvote

Anonymous commented on September 14, 2024
This material is a comprehensive, excellent study guide rather than just a brain dump of prior exams.
UNITED STATES
upvote

Anonymous commented on September 14, 2024
This is a thorough, explanatory, simple, yet detailed set of questions covering CISM's entire spectrum. Thanks for all the efforts.
UNITED STATES
upvote