The linear scheduling velocity diagram has the following two-axis:
Answer(s): C
Total float is defined as the amount of time an activity can be delayed without impacting
Answer(s): A
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
Answer(s): B
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
Post your Comments and Discuss AACE International AACE-PSP exam with other Community members:
Mombasa commented on September 14, 2024 Can you all f***ing b**ches post some helpful comments here or share your experience? Anonymous upvote
Anonymous commented on September 14, 2024 This material is a comprehensive, excellent study guide rather than just a brain dump of prior exams. UNITED STATES upvote
Anonymous commented on September 14, 2024 This is a thorough, explanatory, simple, yet detailed set of questions covering CISM's entire spectrum. Thanks for all the efforts. UNITED STATES upvote
Our website is free, but we have to fight against bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the AACE-PSP content, but please register or login to continue.