The linear scheduling velocity diagram has the following two-axis:

  1. Location and crew size
  2. Time and location
  3. Time and rate of progress
  4. Time and crew size

Answer(s): C



Total float is defined as the amount of time an activity can be delayed without impacting

  1. The overall project completion
  2. The buoyancy of a successor activity
  3. The next activity
  4. The end of that activity

Answer(s): A



If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

  1. The Eichleay formula
  2. Historical production rates
  3. Time impact analysis
  4. Black-Scholes model

Answer(s): B



If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

  1. 8 days
  2. 6 days
  3. 4 days
  4. 5 days

Answer(s): B