A work breakdown structure (WBS) is developed because:

  1. It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.
  2. It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans
  3. It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup
  4. It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Answer(s): B



If a project is said to be on a "fast track program/' the fast track method is:

  1. Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work
  2. First completing engineering and procurement, then executing construction
  3. Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance
  4. Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime

Answer(s): A



Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:

  1. Activity ID
  2. WBS Code
  3. Resource
  4. Account number

Answer(s): A



The process of stating goals and determining the most effective way of reaching them is the definition for:

  1. Implementing
  2. Mission Statement
  3. Managing
  4. Planning

Answer(s): D



Page 3 of 29



Post your Comments and Discuss AACE International CCP exam with other Community members:

Marry Clear commented on September 18, 2020
Very easy purcahse process. The material is well formatted and the Xengine Exam Simualtero is very cool and intuative. I am happy with my purcahse
CANADA
upvote