A schedule's late dates are calculated during the:

  1. Loop calculations
  2. Backward pass
  3. Forward pass
  4. Float

Answer(s): B



Which of the following is NOT a type of float?

  1. Total
  2. Negative
  3. Open end
  4. Free

Answer(s): C



The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

  1. Total float
  2. Remaining duration
  3. Free float
  4. Just-in-time scheduling

Answer(s): A



What is a basic element of work or a task that must be performed over a given period of time in order to complete a project called?

  1. WBS element
  2. Activity
  3. Resource
  4. Commodity

Answer(s): B



Page 4 of 29



Post your Comments and Discuss AACE International CCP exam with other Community members:

Marry Clear commented on September 18, 2020
Very easy purcahse process. The material is well formatted and the Xengine Exam Simualtero is very cool and intuative. I am happy with my purcahse
CANADA
upvote