A _______________ contract allows the contractor to freely employ whatever methods and resources it chooses in order to complete the work.

  1. Measured unit price
  2. Cost reimbursable/Fixed fee
  3. Guaranteed maximum price
  4. Lump-sum/Fixed price

Answer(s): D

Explanation:

A lump-sum (fixed price) contract places responsibility for means, methods, and resource selection on the contractor, allowing them full discretion in how the work is executed as long as the agreed scope is completed for the fixed price.



Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

  1. ACWP/BCWP
  2. ACWP/BCWS
  3. BCWS/BCWP
  4. BCWP/ACWP

Answer(s): D

Explanation:

Cost Performance Index measures cost efficiency by comparing the budgeted value of work performed to the actual cost of that work, indicating how much value is earned for each dollar spent.



_______________ is defined as the budget for the cost (work) account times the percent complete for that account.

  1. Forecast
  2. Earned value
  3. Cost to complete
  4. Percent complete

Answer(s): B

Explanation:

Earned value represents the portion of the budgeted cost that corresponds to the work actually completed, calculated by multiplying the cost account budget by the percent of work complete.



If a project is said to be on a “fast track program,” the fast track method is:

  1. First completing engineering and procurement, then executing construction.
  2. Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the schedule that have been based on assumptions regarding the way the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime.
  3. Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/ sequence and duration for all of the work.
  4. Analyzing the project and specifying the basic approach to be used in its execution: segmenting the project into a reasonable number of activities: estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance.

Answer(s): C

Explanation:

Fast-tracking accelerates project delivery by overlapping engineering, procurement, and construction activities so work proceeds in parallel where feasible, reducing overall project duration while maintaining a coordinated sequence and logic.



An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

  1. Costing
  2. Bid shopping
  3. Cost-price analysis
  4. Negotiating a best and final offer

Answer(s): B

Explanation:

Bid shopping occurs when a contractor discloses one vendor’s quoted price to other vendors to induce lower competing bids, with the intent of reducing the originally quoted price.



A contract clause that provides the owner with the right to terminate the contract irrespective of the general contractor’s liability is:

  1. Termination of contract - default
  2. Breach of contract
  3. Termination of contract - convenience
  4. Substantial completion

Answer(s): C

Explanation:

Termination for convenience allows the owner to end the contract at its discretion, without requiring fault or liability on the part of the general contractor.



The measure of number of units completed divided by work-hours consumed is referred to as:

  1. Earned value
  2. Cost performance index (CPI)
  3. Credit work-hours
  4. Productivity

Answer(s): D

Explanation:

Productivity measures output efficiency by comparing the number of units produced to the work-hours required, indicating how effectively labor is being utilized.



When the project plan is implemented:

  1. Activities are carefully monitored and controlled against the baseline
  2. The basis for payment applications is formalized
  3. The forward and backward pass is identified
  4. CPI and SPI can be calculated and reported

Answer(s): A

Explanation:

When a project plan is implemented, execution focuses on monitoring and controlling activities against the approved baseline to ensure performance, schedule, and cost objectives are being met.