Free AD0-E903 Exam Braindumps (page: 9)

Page 8 of 19

Given this information regarding a Task:
· Planned Start Date: May 14
· Actual Start Date: May 14
· Planned Completion Date: May 20
· Projected Completion Date: May 22
· Percent Complete: 50%

· Duration: 5 Days
· Planned Hours: 8 Hours
· Status: In Progress
If today's date were May 19, what would be the Task's progress status?

  1. Behind
  2. On Time
  3. At Risk

Answer(s): C

Explanation:

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as "At Risk." This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.



The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

  1. Start No Later Than
  2. Must Start On
  3. As Late As Possible

Answer(s): C

Explanation:

In Workfront, the "As Late As Possible" task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.



A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.
What should the project manager ask users to do when it comes to completing tasks?

  1. Users do not need to complete tasks when multiple users are assigned.
  2. Mark the task as "Done with my part."
  3. Make an update and tag the project manager.

Answer(s): B

Explanation:

In scenarios where multiple individuals are assigned to a task, Workfront allows each user to mark the task as "Done with my part" to signify their portion of the task is complete. This ensures that progress is tracked for each user, and the task is only marked as complete when all assigned users have finished their work.



What is unique to a Scrum iteration?

  1. Backlog of stories and issues
  2. Workload Balancer for assigning users to tasks
  3. Burndown Chart

Answer(s): C

Explanation:

A Burndown Chart is a visual representation of work remaining versus time in a Scrum iteration. It is unique to agile methodologies like Scrum and is used to track the team's progress during a sprint. The chart helps teams visualize how much work is left to complete the sprint goal, making it a critical tool in Scrum.






Post your Comments and Discuss Adobe AD0-E903 exam with other Community members:

AD0-E903 Discussions & Posts