Considering the SCOR Model of supply chain operations, which of the following key management processes does assessing the ability of the suppliers to supply resources fall into?

  1. Plan.
  2. Source.
  3. Make.
  4. Deliver.

Answer(s): A

Explanation:

Choice "a" is correct. The process of planning consists of developing a way to properly balance aggregate demand and aggregate supply within the goals and objectives of the firm and plan for the necessary infrastructure. Assessing the ability of the suppliers to supply resources is part of the "plan" process.
Choices "b", "c", and "d" are incorrect, per the above Explanation.



Considering the SCOR Model of supply chain operations, which of the following key management processes does implementing changes in engineering fall into?

  1. Plan.
  2. Source.
  3. Make.
  4. Deliver.

Answer(s): C

Explanation:

Choice "c" is correct. The "make" process encompasses all the activities that turn the raw materials into finished products that are produced to meet a planned demand. Implementing changes in the engineering process falls into the "make" process.
Choices "a", "b", and "d" are incorrect, per the above Explanation.



Considering the SCOR Model of supply chain operations, which of the following key management processes does collecting and processing vendor payments fall into?

  1. Plan.
  2. Source.
  3. Make.
  4. Deliver.

Answer(s): B

Explanation:

Choice "b" is correct. Once demand has been planned, it is necessary to procure the resources required to meet it and to manage the infrastructure that exists for the sources. Collecting and processing vendor payments falls into the "source" process.
Choices "a", "c", and "d" are incorrect, per the above Explanation.



In which stage of supply chain management will management move away from simple consolidation of its operations to an internally-integrated supply chain, which all work together towards the main business issue of the cost of customer service?

  1. Cross-functional teams.
  2. Integrated enterprise.
  3. Extended supply chain.
  4. Supply chain communities.

Answer(s): B

Explanation:

Choice "b" is correct. In the integrated enterprise stage of supply chain management, the firm's management will move away from simple consolidation of its operations to an internally-integrated supply chain, which all work together towards the main business issue of the cost of customer service.
Choice "a" is incorrect. In the cross-functional teams stage of supply chain management, the firm's management will turn its attention to consolidation of the various departments that make up operations in order to solve the firm's problems, and the focus will be on customer service.
Choice "c" is incorrect. In the extended supply chain stage of supply chain management, integration moves external to the firm to involve those outside the firm who are able to work as a unified team in an attempt to obtain slow, profitable growth.
Choice "d" is incorrect. In the supply chain communities stage of supply chain management, the extended supply chain forms a single competitive entity with a synchronized supply chain and a complex system of networks.



Page 57 of 132



Post your Comments and Discuss AICPA CPA-Business exam with other Community members:

Venkatesh commented on September 08, 2023
I don't see Internal Control/Information technology related questions
UNITED STATES
upvote

Jay jain commented on May 25, 2023
This is nice platform
Anonymous
upvote