Capacity requirements planning (CRP) is applicable primarily In companies operating In an environment where:
Answer(s): D
Capacity requirements planning (CRP) is a technique that calculates the capacity needed to produce the planned orders generated by material requirements planning (MRP). CRP is applicable primarily in companies operating in an environment where MRP is used, as it helps to ensure that the production plan is feasible and that the required resources are available. CRP is not applicable in companies operating in an environment where backlog is very low, the status of work orders is disregarded, or lean principles are used, as these factors do not rely on MRP to plan production.
Capacity Requirements Planning | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM
Which of the following statements is true about the mean time between failures (MTBF) measure?
Answer(s): C
Mean time between failures (MTBF) is the average time that elapses from one unplanned breakdown to the next, under normal operating conditions. It is a useful measure of reliability because it indicates how long a repairable system typically operates before failing. Reliability is the absence of unplanned downtime, and MTBF measures how often a system stops performing as expected. The other statements are not true about MTBF. MTBF is not used for non-repairable products, as they cannot be fixed and put back into operation after a failure. For non-repairable products, mean time to failure (MTTF) is used as a measure of reliability. MTBF is not proportional to quality, as quality is a broader concept that encompasses not only reliability, but also performance, durability, and customer satisfaction. MTBF is not the same as operating life or service life, as they refer to the total time that a system can function before reaching the end of its useful life, while MTBF refers to the average time between failures within the operating life.
Mean Time Between Failures (MTBF): How to Calculate & Increase, APICS CPIM 8 Planning and Inventory Management | ASCM
The master schedule is an Important tool in the sales and operations planning (S&OP) process because it:
The master schedule is an important tool in the sales and operations planning (S&OP) process because it balances supply and demand at the product mix level. The master schedule is a detailed plan that specifies the quantity and timing of each end item or product family to be produced. It is derived from the aggregate production plan, which is the output of the S&OP process. The master schedule helps to translate the aggregate plan into specific product requirements and to allocate the available capacity to meet the demand. The master schedule also provides input to the material requirements planning (MRP) and capacity requirements planning (CRP) systems, which further refine the production plan at the component and resource levels. The other statements are not true about the master schedule. The master schedule does not represent the forecast before changes are made in S&OP, as the forecast is an input to the S&OP process, not an output. The master schedule does not represent the forecast with less detail, as the master schedule is more detailed than the forecast, which is usually expressed in aggregate terms. The master schedule does not balance supply and demand at the sales volume level, as the sales volume level is the level of the aggregate production plan, not the master schedule.
Master Schedule | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM
Check sheets can be used to:
Answer(s): A
Check sheets are simple tools that allow data to be collected and recorded in an organized manner. Check sheets can be used to determine the frequency of a defect and the time period between occurrences by counting and categorizing the number of defects that occur over a specified time interval. Check sheets can also help to identify the causes and patterns of defects, and to monitor the effectiveness of improvement actions. The other statements are not true about check sheets. Check sheets do not provide a quick method to identify if possible defects exist, as they require data collection and analysis. Check sheets do not allow improvement teams to see if action items are being completed on time, as they are not designed to track the progress of tasks. Check sheets do not provide an indication of correlation between defects, as they do not measure the relationship between variables.
Check Sheet | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM
The primary reason for tracing a component with scheduling problems to Its master production schedule (MPS) item is to:
The primary reason for tracing a component with scheduling problems to its master production schedule (MPS) item is to determine if a customer order will be impacted. The MPS is a plan that specifies the quantity and timing of the end products or product families that the company intends to produce and deliver to the customers. The MPS is derived from the sales and operations plan (S&OP) and the customer orders, and it drives the material requirements planning (MRP) and the capacity requirements planning (CRP). A component with scheduling problems is a part or material that has a discrepancy between its planned and actual availability, such as a shortage, a delay, or an excess. Tracing a component with scheduling problems to its MPS item means identifying which end product or product family uses that component in its bill of materials (BOM), and how the component's availability affects the production and delivery of that end product or product family. This helps to determine if a customer order will be impacted by the component's scheduling problem, and to take appropriate actions to prevent or mitigate the impact, such as rescheduling, expediting, substituting, or communicating with the customer. The other options are not correct, as they are not the primary reason for tracing a component with scheduling problems to its MPS item, but rather possible actions or outcomes of the tracing process:Revising the rough-cut capacity plan is a possible action that may result from tracing a component with scheduling problems to its MPS item, if the component's availability affects the capacity of the critical resources that are needed to produce the MPS item. Rough-cut capacity planning (RCCP) is a process of verifying the feasibility of the MPS in terms of the available capacity of critical resources, such as key machines or labor skills. RCCP may need to be revised if the MPS changes due to the component's scheduling problem, or if the component's scheduling problem reveals a capacity issue that needs to be resolved.Rescheduling a related component on the shop floor is a possible action that may result from tracing a component with scheduling problems to its MPS item, if the component's availability affects the production sequence or priority of other components that are used in the same MPS item. Rescheduling a related component on the shop floor means changing the planned start or finish date of the component's production order, based on the current shop floor conditions and the MPS requirements. Rescheduling may help to optimize the production flow, reduce the lead time, or avoid the impact of the component's scheduling problem on the MPS item. Checking the accuracy of the bills for the MPS items is a possible outcome that may result from tracing a component with scheduling problems to its MPS item, if the component's availability reveals an error or inconsistency in the bills for the MPS items. Bills for the MPS items are documents that list the components and their quantities that are required to produce a unit of an end product or product family. Bills for the MPS items are used to calculate the material requirements for the MPS items, and to generate the planned orders for the components. Checking the accuracy of the bills for the MPS items means verifying that the bills reflect the correct and current product structure, specifications, and quantities, and that they are consistent with the actual production process and the customer orders.
[CPIM Part 2 - Section A - Topic 1 - Sales and Operations Planning] [CPIM Part 2 - Section A - Topic 2 - Capacity Planning] Master Production Schedule (MPS)What is a Component? | Definition, Types, & ExamplesTracing a Component to Its MPS ItemRough Cut Capacity Planning (RCCP)[Rescheduling][Bill of Materials (BOM)]