The step for preparing MPS is/are:

  1. Develop a preliminary MPS
  2. Check the preliminary MPS against available capacity
  3. Resolve differences between the preliminary MPS and capacity availability
  4. All of these

Answer(s): D



Which of the following criteria is used to judge MPS?

  1. Resource use
  2. Customer service
  3. Cost
  4. All of these

Answer(s): D



Suppose company manufactures paint from a base color and adds tints to arrive at the final color. Suppose there are 10 tints and a final color is made by mixing any three of them with the base. There are 70 possible colors (10*9*8=720). Forecasting and planning production for 720 items is a difficult task. It is much easier if:

  1. Production is planned at the level of the base color and the 10 tints. There are then only10 items with which to deal: the base color and each of the 10 tints.
  2. Once a customer's order is received, the base color and the required tints can be combined (assembled) according to the order
  3. MPS is done at the component level
  4. None of these

Answer(s): A,B



The planning horizon is the time span for which plans are made. It must cover a period at least equal to the time required to accomplish the plan. For Mater production scheduling, the minimum planning horizon is:

  1. The longest cumulative or end-t-end lead time (LT)
  2. The shortest lead time
  3. The difference between the productions of two different batches
  4. None of these

Answer(s): A



Page 24 of 148



Post your Comments and Discuss APICS CPIM exam with other Community members:

Parsad commented on October 23, 2020
I asked for more discount as I needed to buy 3 exams. They gave me 35% discount The code is 35%OFF for anyone who wants to use.
INDIA
upvote