Reducing set up time will affect item lead time and throughput in which of the following ways?

  1. Lead time will increase, throughput will decrease
  2. Lead time will increase, throughput will increase
  3. Lead time will decrease, throughput will increase
  4. Lead time will decrease, throughput will decrease

Answer(s): C



A production rate based on customer demand is called:

  1. cycle time.
  2. takt time.
  3. lead time.
  4. queue time.

Answer(s): B



An electronic board that provides visibility on the production floor is:

  1. andon.
  2. anova.
  3. ANSI.
  4. alpha factor.

Answer(s): A



Which of the following issues would be of greatest concern for a company choosing to reduce its finished goods inventory?

  1. Long production changeover time
  2. Customer service expectations
  3. Product quality requirements
  4. Product shelf life constraints

Answer(s): B