If an operation on a routing is performed out of sequence and the change in sequence is not reported to the formal system, which of the following situations will occur?

  1. An alternate routing will be created.
  2. The capacity requirements planning data will be inflated.
  3. The order will appear on a dispatch list in the wrong work center.
  4. The error will be corrected by cost accounting.

Answer(s): C



Which of the following concepts is a reason to create a visual factory?

  1. They are more successful because visual systems are more robust.
  2. They are inexpensive to implement.
  3. They are more successful because they display well for customer visits.
  4. They are successful because they are self-explaining and self-improving.

Answer(s): D



A supplier of roller bearings makes lots of 10, 000 and sorts them automatically according to size. In a typical lot of 10, 000, the sizes break into the following categories:

The product requires rollers on target or, at most, 0.0001 oversize. Experience indicates that 100% must be reinspected before use because the machine inspection lets a few defective units slip through. The supplier should be encouraged to take which of the following actions?

  1. Learn what factors cause variability.
  2. Tighten the inspection criteria.
  3. Seek deviations from Quality Control.
  4. Doubly inspect the rollers

Answer(s): A



Changes in the order quantity result from changes in:

  1. carrying and setup costs.
  2. setup costs and forecast error.
  3. transportation costs and forecast error.
  4. transportation costs and variation in lead time.

Answer(s): A