If the master production schedule is overstated, which of the following short-term actions is most appropriate?

  1. The demand time fence should be moved out.
  2. Lot sizes should be decreased.
  3. Safety stocks should be decreased.
  4. Firm planned orders should be rescheduled.

Answer(s): D



Which of the following factors has the greatest effect on the length of the forecast horizon?

  1. Cumulative product lead time
  2. Purpose of the forecast
  3. Frequency of forecast revision
  4. Size of forecast period

Answer(s): B



Which of the following actions is best for a company to take when a 2-week plant shutdown for retooling is planned for the next year?

  1. Increase planned production.
  2. Increase material requirements planning safety-stock levels.
  3. Decrease the planned sales level during the shutdown.
  4. Alter the strategic plan.

Answer(s): A



Which of the following is typically an output of the master scheduling process?

  1. Sales forecasts
  2. Resource requirements plans
  3. Interplant demands
  4. Projected available balances

Answer(s): D