Which of the following priority rules is most consistent with the objective of meeting due dates?

  1. First-come-first-served
  2. Shortest processing time (SPT)
  3. Fewest operations remaining
  4. Slack time per operation

Answer(s): D

Explanation:

The priority rule that is most consistent with the objective of meeting due dates is slack time per operation. Slack time per operation is a priority rule that assigns a priority index to each job based on the ratio of the remaining slack time to the remaining number of operations. Slack time is the difference between the due date and the expected completion time of a job. A lower ratio means a higher priority, as it indicates that the job has less slack time per operation and is more likely to be late. Slack time per operation is a dynamic priority rule, as it updates the priority index after each operation is completed. Slack time per operation can help minimize the number of tardy jobs and the average tardiness of jobs, as it gives preference to the jobs that are closer to their due dates and have more operations left.
First-come-first-served (FCFS) is not a priority rule that is consistent with the objective of meeting due dates. FCFS is a priority rule that processes jobs in the order of their arrival or release times. FCFS is a simple and fair rule, but it ignores the processing times and due dates of jobs. FCFS can result in poor due date performance, as it can delay urgent or short jobs behind long or non-urgent jobs.
Shortest processing time (SPT) is not a priority rule that is consistent with the objective of meeting due dates. SPT is a priority rule that processes jobs in ascending order of their processing times. SPT is an effective rule for minimizing the average flow time and work-in-process inventory of jobs, as it clears out small jobs quickly and reduces congestion in the system. However, SPT does not consider the due dates of jobs, and it can make long or urgent jobs late. Fewest operations remaining is not a priority rule that is consistent with the objective of meeting due dates. Fewest operations remaining is a priority rule that processes jobs in ascending order of their remaining number of operations. Fewest operations remaining is a rule that can reduce the variability and complexity of jobs, as it tends to complete jobs faster and reduce their flow times. However, fewest operations remaining does not take into account the slack times or due dates of jobs, and it can make urgent or short jobs late.



When a certified supplier's delivery performance declines, a company should respond initially by:

  1. tightening performance criteria for the supplier.
  2. establishing a temporary buffer of finished goods inventory at the supplier.
  3. communicating with the supplier to investigate the source of the problem.
  4. increasing the standard lead time of the component to allow for supplier delays.

Answer(s): C

Explanation:

When a certified supplier's delivery performance declines, a company should respond initially by communicating with the supplier to investigate the source of the problem. A certified supplier is a supplier that has met certain quality, delivery, and service standards and has been approved by the company to supply goods or services without inspection or testing. A certified supplier is expected to maintain a high level of performance and reliability, as well as to report any issues or deviations that may affect the delivery process. However, sometimes a certified supplier may experience a decline in delivery performance, which can cause delays, disruptions, or dissatisfaction for the company and its customers.
The best way to deal with a decline in delivery performance from a certified supplier is to communicate with the supplier and find out the root cause of the problem. Communication is essential for maintaining a good relationship with the supplier and for resolving any issues or conflicts that may arise. Communication can help the company and the supplier to understand each other's expectations, needs, and challenges, as well as to identify and implement corrective actions or preventive measures. Communication can also help to restore trust and confidence between the parties and to prevent further deterioration of performance. Tightening performance criteria for the supplier is not an appropriate initial response when a certified supplier's delivery performance declines. Tightening performance criteria means imposing stricter standards or requirements on the supplier, such as reducing lead times, increasing penalties, or demanding more frequent reports. Tightening performance criteria may seem like a way of holding the supplier accountable and motivating them to improve their performance, but it can also have negative consequences. Tightening performance criteria can create more pressure and stress for the supplier, which can affect their quality, productivity, or morale. It can also damage the relationship with the supplier, as it may signal a lack of trust, respect, or cooperation from the company.
Establishing a temporary buffer of finished goods inventory at the supplier is not an effective initial response when a certified supplier's delivery performance declines. Establishing a temporary buffer of finished goods inventory means storing extra units of products at the supplier's location to compensate for any delays or shortages in delivery. Establishing a temporary buffer of finished goods inventory may seem like a way of ensuring availability and continuity of supply, but it can also have drawbacks. Establishing a temporary buffer of finished goods inventory can increase inventory costs, such as holding costs, transportation costs, or obsolescence costs. It can also reduce inventory visibility and control, as it may be difficult to track or manage the inventory at the supplier's location. Moreover, establishing a temporary buffer of finished goods inventory does not address the root cause of the decline in delivery performance, but rather masks or postpones it. Increasing the standard lead time of the component to allow for supplier delays is not a suitable initial response when a certified supplier's delivery performance declines. Increasing the standard lead time of the component means extending the time between placing an order and receiving it from the supplier. Increasing the standard lead time of the component may seem like a way of adjusting to the decline in delivery performance and avoiding late deliveries, but it can also have disadvantages. Increasing the standard lead time of the component can reduce customer satisfaction and loyalty, as it may result in longer waiting times or missed deadlines for the customers. It can also reduce operational efficiency and flexibility, as it may limit the ability to respond to changes in demand or supply. Furthermore, increasing the standard lead time of the component does not solve the problem of the decline in delivery performance, but rather accepts or tolerates it. Reference := Supplier Performance Metrics and Scorecard - IADC.org, Delivery Performance Explained (Measures, KPIs, and How to Improve), How to manage supplier performance - gatekeeperhq.com



A company's competitive business strategy is based on offering customized products or features and a rapid response to market shifts. The company's process technology and equipment should be characterized by which of the following combinations?

  1. Continuous flow processes and a high degree of fixed automation
  2. Product-independent processes with parallel production lines
  3. Product-independent processes and flexible automation
  4. Product-dependent processes and automation based on product volume

Answer(s): C

Explanation:

A company's process technology and equipment should be characterized by product-independent processes and flexible automation if its competitive business strategy is based on offering customized products or features and a rapid response to market shifts. Product-independent processes are processes that can produce a variety of products or features without requiring major changes or adjustments in the production system. Flexible automation is a type of automation that can adapt to different product specifications or volumes by using programmable or reconfigurable machines, robots, or software. Product-independent processes and flexible automation can enable a company to offer customized products or features and a rapid response to market shifts by allowing it to:
Produce small batches or single units of products or features that meet specific customer needs or preferences.
Switch quickly and easily between different products or features without losing time or efficiency. Incorporate new technologies, materials, or designs into the production system without disrupting the existing operations.
Respond to changes in demand or supply by adjusting the production capacity or output accordingly. Continuous flow processes and a high degree of fixed automation are not suitable for a company's process technology and equipment if its competitive business strategy is based on offering customized products or features and a rapid response to market shifts. Continuous flow processes are processes that produce products or features in a continuous and uninterrupted manner, without any breaks or buffers between the stages. Fixed automation is a type of automation that uses specialized machines or equipment that are designed to perform a specific task or operation. Continuous flow processes and fixed automation can enable a company to achieve high efficiency,

productivity, and quality, but they also have some limitations, such as:
They are suitable for producing large volumes of standardized products or features that have stable and predictable demand.
They are difficult and costly to modify or change when there is a need to produce different products or features or to incorporate new technologies, materials, or designs. They are inflexible and rigid when there are variations or fluctuations in demand or supply, as they cannot adjust the production capacity or output easily. Product-independent processes with parallel production lines are not appropriate for a company's process technology and equipment if its competitive business strategy is based on offering customized products or features and a rapid response to market shifts. Product-independent processes with parallel production lines are processes that use multiple identical machines or equipment that can produce the same product or feature simultaneously. Product-independent processes with parallel production lines can enable a company to increase its production capacity and output, but they also have some drawbacks, such as:
They are suitable for producing high volumes of standardized products or features that have high and constant demand.
They are inefficient and wasteful when there is a need to produce different products or features or to incorporate new technologies, materials, or designs, as they require duplication of resources and equipment.
They are redundant and unnecessary when there are variations or fluctuations in demand or supply, as they create excess inventory or idle capacity.
Product-dependent processes and automation based on product volume are not optimal for a company's process technology and equipment if its competitive business strategy is based on offering customized products or features and a rapid response to market shifts. Product-dependent processes are processes that can produce only one type of product or feature, or that require significant changes or adjustments in the production system to produce different products or features. Automation based on product volume is a type of automation that uses different machines or equipment depending on the volume of production required for each product or feature. Product- dependent processes and automation based on product volume can enable a company to optimize its production costs and quality, but they also have some disadvantages, such as:
They are suitable for producing low volumes of specialized products or features that have low variability and uncertainty in demand.
They are complex and time-consuming when there is a need to produce different products or features or to incorporate new technologies, materials, or designs, as they require frequent changes or setups in the production system.
They are unresponsive and slow when there are variations or fluctuations in demand or supply, as they cannot adapt the production capacity or output quickly. Reference := Process Technology - an overview | ScienceDirect Topics, Flexible Automation - an overview | ScienceDirect Topics, Continuous Flow Process - an overview | ScienceDirect Topics, Fixed Automation - an overview | ScienceDirect Topics, Parallel Production Line - an overview | ScienceDirect Topics, Product Dependent Process - an overview | ScienceDirect Topics



Which of the following measurements indicates there may be bias in the forecast model?

  1. Mean absolute deviation (MAD)
  2. Standard deviation
  3. Tracking signal
  4. Variance

Answer(s): C

Explanation:

The measurement that indicates there may be bias in the forecast model is the tracking signal. The tracking signal is a ratio of the cumulative forecast error to the mean absolute deviation (MAD). The cumulative forecast error is the sum of the differences between the forecasted and actual values over a period of time. The MAD is the average of the absolute values of the forecast errors. The tracking signal can help detect and measure the bias of a forecast model by comparing the magnitude and direction of the forecast errors. A positive tracking signal indicates that the forecast model is consistently over-forecasting, while a negative tracking signal indicates that the forecast model is consistently under-forecasting. A zero tracking signal indicates that there is no bias in the forecast model. A rule of thumb is that if the tracking signal exceeds a certain threshold, such as ±4, then there is a significant bias in the forecast model that needs to be corrected. The other measurements do not indicate bias in the forecast model, but rather other aspects of the forecast accuracy or variability. The MAD is a measure of the average error or deviation of the forecast model from the actual values. The MAD does not indicate bias, as it does not consider the direction or sign of the errors. A low MAD indicates a high accuracy of the forecast model, while a high MAD indicates a low accuracy of the forecast model. The standard deviation is a measure of the dispersion or variation of the forecast errors around their mean. The standard deviation does not indicate bias, as it does not consider the direction or sign of the errors. A low standard deviation indicates a low variability or uncertainty of the forecast model, while a high standard deviation indicates a high variability or uncertainty of the forecast model. The variance is a measure of the squared deviation or dispersion of the forecast errors around their mean. The variance does not indicate bias, as it does not consider the direction or sign of the errors. The variance is related to the standard deviation, as it is equal to the square of the standard deviation. A low variance indicates a low variability or uncertainty of the forecast model, while a high variance indicates a high variability or uncertainty of the forecast model. Reference := Forecast KPI: RMSE, MAE, MAPE & Bias | Towards Data Science, A Critical Look at Measuring and Calculating Forecast Bias ­ Demand Planning, Forecast bias - Wikipedia



The results from responding to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes is called:

  1. bullwhip effect.
  2. supply and demand.
  3. process train.
  4. forward integration.

Answer(s): A

Explanation:

The results from responding to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes is called the bullwhip effect. The bullwhip effect is a phenomenon that occurs when small changes in demand at the downstream end of the supply chain (such as retailers or customers) cause larger and larger fluctuations in demand at the upstream end of the supply chain (such as wholesalers, distributors, or manufacturers). The bullwhip effect can create inefficiencies, waste, and costs in the supply chain, as well as reduce customer satisfaction and profitability. One of the causes of the bullwhip effect is the response to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes. Lead time is the time between placing an order and receiving it from a supplier. Lot size is the quantity of units ordered or produced at a time.
When there is uncertainty or variability in demand or supply, such as due to seasonality, promotions, disruptions, or forecasting errors, some supply chain members may try to cope by exaggerating lead times and increasing lot sizes. For example, a retailer may increase its safety stock or reorder point to avoid stockouts or delays, or a manufacturer may produce more than needed to take advantage of economies of scale or discounts. However, these actions can have unintended consequences, as they can distort the demand information and amplify the demand variability along the supply chain. This can result in excess inventory, low inventory turnover, high holding costs, poor service levels, lost sales, obsolete products, or capacity issues.
To prevent or reduce the bullwhip effect caused by responding to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes, some possible solutions are:
Improving communication and collaboration among supply chain members to share accurate and timely demand information and forecasts.
Reducing lead times and lot sizes by using lean production techniques, just-in-time inventory systems, or quick response methods.
Implementing vendor-managed inventory (VMI) systems, where suppliers are responsible for managing and replenishing the inventory of their customers based on their actual consumption data. Adopting advanced technologies, such as radio-frequency identification (RFID), artificial intelligence (AI), or blockchain, to enhance visibility, traceability, and coordination in the supply chain. Reference := Bullwhip Effect: Meaning, Example, Impact - Investopedia, Bullwhip Effect - What Is It, Causes, Supply Chain, Examples, Bullwhip Effect: Example, Causes, and Impact on Supply Chain