According to Davis- what are the biggest problems of major implementations?
I) Not a strong project manager
II) Conflicting interpretations of business goals
III) Uncoordinated choosing and implementation of changes

  1. I & III Only
  2. II & III Only
  3. I & II Only
  4. I, II, & III

Answer(s): B

Explanation:

2 biggest problems of major implementation Davis
1. Conflicting interpretations of business goals
2. Uncoordinated choosing and implementation of changes



What measures net profit over the cost of all capital to create the profit?

  1. Cash to Book Value
  2. Economic Value Added
  3. Inventory Turns
  4. Earnings Before Interest and Taxes (EBIT)

Answer(s): B

Explanation:

Economic Value Added measures net profit over the cost of all capital to create the profit?



When each link in the supply chain builds in extra safety in the planned requirements creates what?

  1. Higher Quality
  2. Reduced Inventory
  3. Higher Customer Satisfaction
  4. Bullwhip effect

Answer(s): D

Explanation:

When each link in the supply chain builds in extra safety in the planned requirements creates the bullwhip effect. Synchronization across the supply chain is the only way to resolve this bullwhip effect.



Supplier Relationship Managements MOST important intent is to what?

  1. Reduce Unnecessary Inventory
  2. Quicker Lead Time
  3. Higher Quality
  4. Reduce Material Cost

Answer(s): A

Explanation:

Supplier Relationship Managements MOST important intent is to reduce inventory. By reducing unneeded inventory can have quicker lead times and lower material costs.