A team complains that many of their issues are in the Closed status, but do not have a resolution set, which causes problems with reporting. The project uses a single workflow.
You want to set the resolution to Done on all existing issues in the Closed status. Which combination of workflow elements and a bulk operation will achieve this?
- A temporary transition and a trigger
An Edit Issues bulk operation - A temporary transition and a post function
A Transition Issues bulk operation - A screen and the Resolution field
A Move Issues bulk operation - A screen and a custom field
An Edit Issues bulk operation - A temporary transition and a screen
An Edit Issues bulk operation