Analyze the Epic Report shown.Identify why the epic completion date is hard to predict.
Answer(s): D
The epic completion date is hard to predict because the team adds new stories throughout the epic.This means that the scope of the epic is not fixed and can change over time. The Epic Report shows the progress of an epic by comparing the estimated amount of work to the completed work. The report also shows a projected completion date based on the team's average velocity. However, if the team keeps adding new stories to the epic, the estimated amount of work will increase and the projected completion date will be pushed further. This makes it difficult to plan and deliver the epic within a certain timeframe.
Managing Jira Projects Data Center and Server: Certification Bundle, Epic Report
A product owner is responsible for two scrum teams. He needs to:· see a snapshot displaying key sprint information like time elapsed and percentage of scope change · monitor the overall progress of the next release to determine if it will ship on time Which two gadgets will show this information? (Choose two.)
Answer(s): A,C
The Version Report and the Sprint Health Gadget are two gadgets that can show the information that the product owner needs. The Version Report shows the progress of a version by comparing the estimated amount of work to the completed work. The report also shows a projected release date based on the team's average velocity. The product owner can use this report to monitor the overall progress of the next release and determine if it will ship on time. The Sprint Health Gadget shows a snapshot of key sprint information such as time elapsed, percentage of scope change, sprint goal, and team members' availability. The product owner can use this gadget to see how each scrum team is performing in their current sprint and identify any issues or risks.
Managing Jira Projects Data Center and Server: Certification Bundle, Version Report, Sprint Health Gadget
The head of customer service wants to identity potential bottlenecks in the support workflow of her teams in the last three months. Which report provides this information?
Answer(s): C
The Cumulative Flow Diagram is the report that provides the information that the head of customer service wants. The Cumulative Flow Diagram is a tool that visualizes the quantity and distribution of work items along different stages of a process. The report shows how many work items are in each stage at any given time, and how they flow from one stage to another. The report can help identify potential bottlenecks in the support workflow by showing where work items accumulate or stagnate over time. For example, if the report shows a sudden increase or a wide band of work items in the "Waiting for Customer" stage, it may indicate that the customers are not responding quickly enough or that the support team is not following up effectively. The report can also help monitor the overall progress and performance of the support teams by showing the total number of work items created, resolved, and remaining over time.
Managing Jira Projects Data Center and Server:Certification Bundle, Cumulative Flow Diagram
A Scrum team working on multiple epics complains that they are constantly being pushed to complete more work than they think can be completed. Apparently, the product owner has constantly overloaded each of the past 8 sprints. Which single report can instantly prove their statement?
Answer(s): A
Post your Comments and Discuss ATLASSIAN ACP-610 exam with other Community members:
Kumar commented on September 01, 2024 Nice qs and Anonymous upvote
Our website is free, but we have to fight against bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the ACP-610 content, but please register or login to continue.