Managing Jira Projects for Data Center and Server Certification Questions 26–30 (page: 7)

Updated On: 9-Feb-2026

Gen prioritizes and triages support requests as soon as they come in. She now wants to use drag- and-drop to:
· quickly assign and transition them to in Progress
· instantly associate them with Epics

Which board view will meet these requirements?

  1. Scrum backlog
  2. Kanban board
  3. Kanban backlog
  4. Active sprints

Answer(s): B

Explanation:

A Kanban board is the best option for Gen to prioritize and triage support requests using drag-and- drop. A Kanban board allows Gen to quickly assign issues to herself or other team members by dragging them to the appropriate column. She can also transition issues to In Progress by moving them across the workflow. Additionally, she can instantly associate issues with Epics by dragging them to the Epic panel on the right side of the board. A Kanban board also provides a visual overview of the current status and progress of the support requests.


Reference:

Managing Jira Projects Data Center and Server: Certification Bundle, Configuring projects | Administering Jira applications Data Center and ..., [Working with issues | Jira Software Cloud]



The release manager is requesting a list of all issues included in a particular sprint.
Which report will provide this information?

  1. Control Chart
  2. Release Burndown
  3. Version Report
  4. Sprint Report
  5. Average Age Report

Answer(s): D

Explanation:

A Sprint Report is the best report to provide a list of all issues included in a particular sprint. A Sprint Report shows the scope, status, and completion date of each sprint. It also displays a breakdown of the completed, incomplete, and added issues in the sprint. The release manager can easily view the list of incomplete issues in the Issue Navigator by clicking on the View in Issue Navigator link at the bottom of the report. A Sprint Report also helps to track the team's performance and identify any scope changes during the sprint.


Reference:

Managing Jira Projects Data Center and Server:
Certification Bundle, [Sprint Report | Jira Software Cloud]



Your team failed to meet their last sprint commitment and you want to investigate further. You need an agile report that:
· shows you a list of the incomplete issues in the sprint · allows you to quickly view that list in the Issue Navigator

Which report meets this need?

  1. Burndown Chart
  2. Control Chart
  3. Cumulative Flow Diagram
  4. Sprint Report
  5. Velocity Chart

Answer(s): D

Explanation:

A Sprint Report is also the best report to meet this need. As explained above, a Sprint Report shows a list of the incomplete issues in the sprint and allows you to quickly view that list in the Issue Navigator. A Sprint Report can help you investigate why your team failed to meet their last sprint commitment by showing you how many issues were added or removed during the sprint, how many issues were completed or not completed, and how much work was carried over to the next sprint.


Reference:

Managing Jira Projects Data Center and Server: Certification Bundle, [Sprint Report | Jira Software Cloud]



Analyze the Epic Report shown.



Identify why the epic completion date is hard to predict.

  1. Most stories aren't estimated until the end of the epic
  2. The configured Working Days for the board are unrealistic.
  3. The team is using issue count for their estimation statistic.
  4. The team adds new stories throughout the epic.

Answer(s): D

Explanation:

The epic completion date is hard to predict because the team adds new stories throughout the epic.

This means that the scope of the epic is not fixed and can change over time. The Epic Report shows the progress of an epic by comparing the estimated amount of work to the completed work. The report also shows a projected completion date based on the team's average velocity. However, if the team keeps adding new stories to the epic, the estimated amount of work will increase and the projected completion date will be pushed further. This makes it difficult to plan and deliver the epic within a certain timeframe.


Reference:

Managing Jira Projects Data Center and Server: Certification Bundle, Epic Report



A product owner is responsible for two scrum teams. He needs to:

· see a snapshot displaying key sprint information like time elapsed and percentage of scope change · monitor the overall progress of the next release to determine if it will ship on time Which two gadgets will show this information? (Choose two.)

  1. Version Report
  2. Issues in progress
  3. Sprint Health Gadget
  4. Activity Stream
  5. Projects
  6. Filter Results

Answer(s): A,C

Explanation:

The Version Report and the Sprint Health Gadget are two gadgets that can show the information that the product owner needs. The Version Report shows the progress of a version by comparing the estimated amount of work to the completed work. The report also shows a projected release date based on the team's average velocity. The product owner can use this report to monitor the overall progress of the next release and determine if it will ship on time. The Sprint Health Gadget shows a snapshot of key sprint information such as time elapsed, percentage of scope change, sprint goal, and team members' availability. The product owner can use this gadget to see how each scrum team is performing in their current sprint and identify any issues or risks.


Reference:

Managing Jira Projects Data Center and Server: Certification Bundle, Version Report, Sprint Health Gadget