Free AVIXA-CTS Exam Braindumps
Certified Technology Specialist Questions 46–50 (page: 11)

Updated On: 10-Feb-2026

[Developing AV Solutions]
An event planner for a banquet surrounding a swimming pool has requested that the pool be lit in the client's colors using underwater lighting.
What does the technician need to consider?

  1. the IP rating of the fixtures
  2. access to a grounded power supply
  3. whether the installing technicians are PADI certified
  4. the ability to physically secure the fixtures underwater

Answer(s): A



[Managing AV Projects]
Which of the following project management activities coordinates project requirements and resources?

  1. project budget
  2. logic model timeline
  3. logic network diagram
  4. project kick-off meeting

Answer(s): C



[Installing AV Systems]
Which type of contract involves ongoing support for an AV system, regardless of the age of the facility or who did the initial installation?

  1. system warranty
  2. service agreement
  3. manufacturer warranty
  4. preventive maintenance

Answer(s): B



[Developing AV Solutions]
A task cannot begin before another task is completed. How is this described in a project task schedule?

  1. requirement
  2. dependency
  3. consequence
  4. determination

Answer(s): B



[Developing AV Solutions]
For a design-bid (tender)-build project, the final step for determining the owner's costs for an AV system is

  1. selecting an Integrator.
  2. performing a needs analysis.
  3. having the owner approve the design.
  4. ensuring the equipment specification is ready for bid.

Answer(s): D



Viewing page 11 of 52
Viewing questions 51 - 55 out of 254 questions


Post your Comments and Discuss Avixa AVIXA-CTS exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!