[Installing AV Systems]
The installation of a complex AV project is planned to be completed within 6 months.
What is the MOST cost-effective plan for ordering the equipment for the project?

  1. Order everything as soon as the contract is signed.
  2. Place the order 5 days before the scheduled day for starting installation.
  3. Order each piece of equipment to be delivered as soon as possible.
  4. Order equipment to be delivered on a "just in time" basis according to the installation schedule.

Answer(s): D



[Developing AV Solutions]
Which microphone type has a basic cardioid pick up pattern?

  1. Type(a)
  2. Type(b)
  3. Type(c)
  4. Type(d)

Answer(s): B



[Conducting a Needs Assessment]
Which of the following aspects should FIRST be considered at an initial site survey for the location of AV racks?

  1. serviceability
  2. available space
  3. access route restrictions
  4. space allowance for future expansion

Answer(s): C



[Developing AV Solutions]
Every item in a room has some acoustic absorption or reflection characteristics. The level of sound absorbed is MOST affected by

  1. distance from the sound source.
  2. ambient sound in the system location.
  3. relative loudness of the source material.
  4. frequency and direction of the source.

Answer(s): D



[Developing AV Solutions]
The limits of the vertical visual field indicate that displays should be positioned where in relation to the viewers' standard line of sight?

  1. center of the image is precisely on-axis
  2. center of the image is at least 10 degrees above
  3. top of the image is no more than 30 degrees above
  4. bottom of the image is no more than 30 degrees below

Answer(s): C