Avixa AVIXA-CTS Exam
Certified Technology Specialist (Page 5 )

Updated On: 7-Feb-2026

[Developing AV Solutions]
The BEST way to ensure that a project is on budget is to

  1. calculate the number of calendars days remaining to completion.
  2. visit the job site and determine the percentage of work completed.
  3. ask the installation team to estimate remaining work to completion.
  4. review accrued labor and material costs against remaining work.

Answer(s): D



[Operating AV Systems]
Maintaining AV operations includes which of the following?

  1. conforming to DISCAS
  2. measuring system SPL
  3. updating control system firmware
  4. comparing NAG and PAG calculations

Answer(s): C



[Developing AV Solutions]
How frequently should a personal fall arrest harness be inspected?

  1. weekly
  2. before each use
  3. at the beginning of each project
  4. at the beginning of each work day

Answer(s): B



[Developing AV Solutions]
When discussing a proposed audiovisual project with a new customer, it is important for the salesperson to FIRST

  1. conduct a survey of end users to determine the project goals.
  2. prepare a detailed layout of the equipment and cabling requirements.
  3. identify the key decision makers and stakeholders in the client's organization.
  4. consult with the project manager to determine the availability of staff to complete the installation.

Answer(s): C



[Developing AV Solutions]
Project documentation states the system must logically Isolate control and media networks.
What piece of network equipment should be used?

  1. router
  2. access point
  3. managed switch
  4. unmanaged switch

Answer(s): C