How would you determine what version of PSA your organization is on?

  1. Go to Setup > Installed Packages > PSA Core
  2. Go to Setup > Installed Packages > PS Enterprise
  3. Go to Setup > Installed Packaqes > FinancialForce Central

Answer(s): A



You have received a requirement to add the "Gantt" button to the Project page layout. Dynamic Forms are not in use. How would you configure this change?

  1. Go to Setup > Custom Settings > Page Preferences > navigate to the "Display Buttons" setting > input "AH" to display all available buttons on the page
  2. Go to Setup > Object Manager > Project > Lightning Record Pages > select the assigned lightning page > Edit the page > navigate to the "Buttons" component > drag the "Gantt" button onto the page
  3. Go to Setup > Object Manager > Project > page layouts > open the assigned page layout > navigate to the "Mobile & Lightning Actions" menu > drag the "Gantt" button onto the page

Answer(s): C



A user is having an issue where the Utilization report has inflated hours. The billable hours, calendar hours, and credited hours are double their actual values.
Which of the following is a possible cause of this issue?

  1. The report filter for "End Date" needs to be edited to a different date range
  2. The report needs to be grouped by Resource
  3. The report needs to be filtered by Time Period Type

Answer(s): C



You configured a new Salesforce approval process on the "Timecard" object.
What is needed to make a user a Timecard approver in this process?

  1. The approver must be in the same role hierarchy as the submitter
  2. The approver must have Read permissions on the "Timecard" object
  3. The approver must be set up as a Delegated Approver for the submitter

Answer(s): C



A manager was looking at utilization for a resource for the last two months. The resource was identified as 80% utilized for each month, but the subtotal section showed 160% for the user for that same two month period.
How can the report be fixed to show 80% instead of 160%?

  1. Adjust the Resource's work calendar to 40 hours and refresh the report
  2. Create a Summary Level formula so the subtotal is calculated and not summed
  3. Set the "Utilization" setting for Target Utilization Approach to "Weighted"

Answer(s): C