A company budgeted £100,000 for labour.

However, feedback indicates that due to the need for overtime, the actual figure is more likely to be £120,000.

What type of feedback is this an example of?

Select the correct answer from the choices below:

  1. Negative feedback
  2. Positive feedback
  3. internal feedback
  4. ExternaI feedback
  5. Substantive feedback

Answer(s): A



Which THREE of the following costs would normally be classified as semi-variable?

  1. Wages of a waitress paid a fixed rate per hour
  2. Salary of a sales executive paid a basic salary and a bonus based on sales level
  3. Advertising costs
  4. Cost of renting a photocopier which is a fixed rental fee plus a charge per copy made
  5. Telephone costs
  6. Royalties paid per unit produced

Answer(s): B,D,E



CORRECT TEXT

GB operates a standard costing system. During the month 24,300 kg of material were used at a standard cost of $2 per kg. The material price variance was $972 adverse.

The actual price per kg was, to 2 decimal places:

  1. $2.08 adverse

Answer(s): A



CORRECT TEXT

Refer to the exhibit.



The following data refers to a manufacturing process for the month of July:
The work in progress is completed as follows:

(a) 100% for material

(b) 80% for labour

(c) 60% for overhead

What is the value of the finished goods?

  1. £13198

Answer(s): A