A medium-sized manufacturing company, which operates in the electronics industry, has employed a firm of consultants to carry out a review of the company’s planning and control systems. The company presently uses a traditional incremental budgeting system and the inventory management system is based on economic order quantities (EOQ) and reorder levels. The company’s normal production patterns have changed significantly over the previous few years as a result of increasing demand for customized products. This has resulted in shorter production runs and difficulties with production and resource planning.

The consultants have recommended the implementation of activity based budgeting and a manufacturing resource planning system to improve planning and resource management.

How will a manufacturing resource planning system improve the planning of purchases and production for the company?

Select ALL the correct answers.

  1. The traditional approach to determine material requirements is to monitor inventories constantly; whenever they fall to a predetermined level, a preset order is placed to replenish them. This traditional approach (involving re-order levels and economic order quantity calculations originates in the pre-computer era.
  2. A manufacturing resource planning approach to the management of all the company’s manufacturing resources including inventory, labour and machine capacity.
  3. It seeks to ensure that resources are available just before they are needed by the next stage of production or dispatch. It also seeks to ensure that resources are delivered only when required so that raw material inventory is kept to a minimum.
  4. The technique will not enable managers to track orders through the manufacturing process and will not assist the purchasing and production control departments to move the right amount of material or sub­assemblies at the right time to the right place.
  5. The correct inventory management system relies on the assumption that there is constant demand. An MRP system begins with the setting of a master production schedule specifying both the timing and quantity demanded of each of the finished goods items and then works backwards to determine the resource requirements at each stage of the production process.
  6. It aims to generate an estimation of materials requirements after taking account of the number of employees quality and waste. The TQS model can be used within MRP provided that the major assumption in the TQS model of constant demand applies.

Answer(s): A,B,C,E



A medium-sized manufacturing company, which operates in the electronics industry, has employed a firm of consultants to carry out a review of the company’s planning and control systems. The company presently uses a traditional incremental budgeting system and the inventory management system is based on economic order quantities (EOQ) and reorder levels. The company’s normal production patterns have changed significantly over the previous few years as a result of increasing demand for customized products. This has resulted in shorter production runs and difficulties with production and resource planning. The consultants have recommended the implementation of activity based budgeting and a manufacturing resource planning system to improve planning and resource management.

What are the benefits for the company that could occur following the introduction of an activity based budgeting system?

Select ALL the correct answers.

  1. Under an activity based budgeting system, resource allocation is linked to the strategic plan and is prepared after considering alternative strategies. This approach ensures that new activities that are required to meet the company’s strategic objectives are included in the budget.
  2. Under a traditional incremental budgeting system the focus is on existing resources and operations. Adjustments are then made for changes in activity and price which results in past inefficiencies being perpetuated. Under an activity based budgeting system, only resources that are needed to perform activities required to meet the budgeted production and sales volumes are included.
  3. Activity based techniques including activity based budgeting focus on the outputs of a process rather than the input to the process. This approach provides a clear framework for understanding the link between costs and the level of activity. It allows the ranking of activities and the determination of how limited resources should be allocated across competing activities.
  4. Activity Based Budgeting Systems present costs under functional headings i.e. the emphasis is on the nature of the cost. The weakness if this approach is that it gives little indication of the link between the level of activity and the cost incurred.
  5. The approach under an Activity based Budgeting System is to make arbitrary cuts in order to meet overall financial targets.

Answer(s): A,B,C



RFT, an engineering company, has been asked to provide a quotation for a contract to build a new engine. The potential customer is not a current customer of RFT, but the directors of RFT are keen to try and win the contract as they believe that this may lead to more contracts in the future. As a result, they intend pricing the contract using relevant costs. The following information has been obtained from a two-hour meeting that the Production Director of RFT had with the potential customer. The Production Director is paid an annual salary equivalent to $1,200 per 8-hour day. 110 square meters of material A will be required. This is a material that is regularly used by RFT and there are 200 square meters currently in inventory. These were bought at a cost of $12 per square meter. They have a resale value of $10.50 per square meter and their current replacement cost is $12.50 per square meter. 30 liters of material B will be required. This material will have to be purchased for the contract because it is not otherwise used by RFT. The minimum order quantity from the supplier is 40 liters at a cost of $9 per liter. RFT does not expect to have any use for any of this material that remains after this contract is completed. 60 components will be required. These will be purchased from HY. The purchase price is $50 per component. A total of 235 direct labour hours will be required. The current wage rate for the appropriate grade of direct labour is $11 per hour. Currently RFT has 75 direct labour hours of spare capacity at this grade that is being paid under a guaranteed wage agreement. The additional hours would need to be obtained by either (i) overtime at a total cost of $14 per hour; or (ii) recruiting temporary staff at a cost of $12 per hour.

However, if temporary staff are used they will not be as experienced as RFT’s existing workers and will require 10 hours supervision by an existing supervisor who would be paid overtime at a cost of $18 per hour for this work. 25 machine hours will be required. The machine to be used is already leased for a weekly leasing cost of $600. It has a capacity of 40 hours per week. The machine has sufficient available capacity for the contract to be completed. The variable running cost of the machine is $7 per hour. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.

Select ALL the true statements.

  1. The cost for the production director meeting was a relevant cost.
  2. Material A was a relevant cost.correct
  3. Material B was a relevant cost.correct
  4. The components are to be purchased from HY at a cost of $50 each. This is a relevant cost because it is future expenditure that will be incurred as a result of the work being undertaken.correct
  5. The machine is currently being leased and it has spare capacity so it will either stand idle or be used on this work. The lease cost will be a relevant cost or $10 per hour.
  6. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour. This is a relevant cost.
  7. The relevant cost is $7010correct
  8. The relevant cost is $7080
  9. The relevant cost is $7100

Answer(s): B,C,D,G



A company has to choose between three mutually exclusive projects. Market research has shown that customers could react to the projects in three different ways depending on their preferences. There is a 30% chance that customers will exhibit preferences 1, a 20% chance they will exhibit preferences 2 and a 50% chance they will exhibit preferences 3. The company uses expected value to make this type of decision.

The net present value of each of the possible outcomes is as follows:


A market research company believes it can provide perfect information about the preferences of customers in this market.

What is the maximum amount that should be paid for the information from the market research company?

  1. $145 000
  2. $140 000
  3. $125 000
  4. $135 000

Answer(s): B