Free PK0-004 Exam Braindumps

A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?

  1. Network diagram
  2. Ishikawa diagram
  3. WBS
  4. Gantt chart

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160



A member of a CCB notices a change request was not approved by the steering committee. Which of the following is the BEST method to handle this situation?

  1. Disapprove the change request.
  2. Evaluate the impact of the change.
  3. Develop a regression plan.
  4. Hold the change request for review

Answer(s): B



A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial.

This would MOST likely impact the project’s: (Choose two.)

  1. environment
  2. scheduling
  3. requirements
  4. effectiveness
  5. scope
  6. budget

Answer(s): B,D



A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?

  1. Provide the next task to the newly freed resource.
  2. Communicate the success to the team.
  3. Notify the project sponsor of the new completion date.
  4. Update the schedule and add lag to the next task.

Answer(s): B



Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)

  1. Business continuity response
  2. Milestone achievement
  3. Incident response
  4. Schedule change
  5. Change request
  6. Stakeholder changes

Answer(s): A,B