You work as a project manager for BlueWell Inc. You are working with your team members on the risk responses in the project.
Which risk response will likely cause a project to use the procurement processes?

  1. Mitigation
  2. Sharing
  3. Exploiting
  4. Acceptance

Answer(s): B



You want to use PGP files for steganography.
Which of the following tools will you use to accomplish the task?

  1. Snow
  2. ImageHide
  3. Blindside
  4. Stealth

Answer(s): D



Fill in the blank:
A ___________plan is a plan devised for a specific situation when things could go wrong.

  1. contingency

Answer(s): A



You are working as a Project Manager in your organization. You are nearing the final stages of project execution, and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

  1. Quantitative risk analysis
  2. Requested changes
  3. Risk audits
  4. Qualitative risk analysis

Answer(s): B



Software Development Life Cycle (SDLC) is a logical process used by the programmers to develop software.
Which SDLC phase meets the following audit objectives? System and data are validated.
System meets all user requirements.
System meets all control requirements.

  1. Definition
  2. Evaluation and acceptance
  3. Initiation
  4. Programming and training

Answer(s): B