Free EX0-008 Exam Braindumps (page: 7)

Page 6 of 15

According to Agile principles, what should be the pace of development?

  1. Fast
  2. Increasing
  3. Sustainable

Answer(s): C



The Product Owner is going on a three-week vacation. The team should be closing the current Sprint and starting a new Sprint at the end of the first week of the Product Owner's vacation.
What is the best way to continue the Scrum rituals in this situation?

  1. Each Scrum team should ideally have two Product Owners to provide cover.
  2. The Product Owner should be requested to delay his vacation by a week.
  3. The Scrum Master should take over and cover for the Product Owner.

Answer(s): C



A Project Manager wants to track not just the rate of progress against tasks, but also the overall morale and happiness of the Scrum team.
What device will help track morale and happiness?

  1. A Gross Happiness index
  2. A Niko-niko calendar
  3. An employee satisfaction survey

Answer(s): B



When is a Sprint complete?

  1. When all of the Product Backlog items are completed.
  2. When all the tasks in the Sprint Backlog are completed.
  3. When the Sprint defined time box ends.

Answer(s): C