PRINCE2 Foundation Exam (PR2F) Questions 51–55 (page: 12)

Updated On: 10-Feb-2026

Who should act as the communication channel between a project and corporate or programme
management?

  1. Project Board
  2. Project Assurance
  3. Project Manager
  4. Project Support

Answer(s): A



Who represents the three project interests on a project?

  1. Project Manager
  2. Project Support
  3. External project stakeholders
  4. Project Board

Answer(s): D



Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

  1. Checkpoint Report
  2. End Stage Report
  3. End Project Report
  4. Product Status Account

Answer(s): B



Which is a purpose of a Project Product Description?

  1. Form part of the Work Package for the project product
  2. Provide the initial project budget to be refined in the Business Case
  3. Document the project mandate and gain approval for the project from the Project Board
  4. Define the quality required of the project's product

Answer(s): D



What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

  1. Directing a Project
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Managing Product Delivery

Answer(s): B



Viewing page 12 of 50
Viewing questions 56 - 60 out of 296 questions