Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

  1. Defined roles and responsibilities
  2. Learn from experience
  3. Manage by exception
  4. Focus on products

Answer(s): B



What product should be used to confirm the version number of ail products in a particular stage?

  1. Issue Register
  2. Product Status Account
  3. Product Description
  4. Configuration Item Record

Answer(s): B



In what product should the quality criteria for a specialist product be recorded?

  1. Quality Management Strategy
  2. Quality Register
  3. Product Description
  4. Project Product Description

Answer(s): C



Which is a purpose of the Risk theme?

  1. Establish a method for the implementation of continuous improvement during the project
  2. Identify, assess and control problems that have occurred
  3. Provide the Project Board with a time-driven control to capture all project risks
  4. Establish a cost-effective procedure to identify, assess and control risks

Answer(s): D



Which is a purpose of an Exception Plan?

  1. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
  2. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
  3. Identify the actions required to recover from the effect of a tolerance deviation
  4. Define the changes which are within the scope of the change budget

Answer(s): C