Which is a type of issue?

  1. A lesson
  2. A request for change
  3. An Exception Report
  4. A risk with an estimated high impact

Answer(s): B



Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,

  1. benefits, progress, risk,
  2. benefits, quality, risk,
  3. change, quality, progress,
  4. benefits, customers, quality,

Answer(s): B



Which task is performed by the Change Authority?

  1. Set a change budget
  2. Approve or reject a request for change within approved limits
  3. Refer changes that exceed budgetary limits to the Project Manager for approval
  4. Update the configuration management system when a change is approved

Answer(s): B



Identify the missing word in the following sentence, A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.

  1. costs
  2. risks
  3. benefits
  4. issues

Answer(s): C



Which process provides the Project Board with the information it requires in order to commit
resources to the project?

  1. Managing Product Delivery
  2. Initiating a Project
  3. Controlling a Stage
  4. Directing a Project

Answer(s): B