Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project
2. Stakeholders may be internal or external to the corporate organization

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true

Answer(s): C



Which is a purpose of quality planning?

  1. Define the structure of the project management team
  2. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
  3. Document approval records for those project products that have met their quality criteria
  4. Produce the Project Plan with resource and schedule information

Answer(s): B



Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.

  1. Change
  2. Plans
  3. Quality
  4. Risk

Answer(s): D



Which product identifies the management stages and timescales of a project?

  1. Project Brief
  2. Project Product Description
  3. Project Plan
  4. Initiation Stage Plan

Answer(s): C



How should the Team Manager report that tolerances are forecast to be exceeded?

  1. Create an Exception Report
  2. Create a Highlight Report
  3. Raise an issue
  4. Grant a concession

Answer(s): C