Which of the following is not a test event?

  1. Functional testing
  2. Negative testing
  3. Unit testing
  4. Acceptance testing

Answer(s): B



Risks associated with prototypes and RAD are:

  1. Incomplete system design
  2. Ineffi cient processing performance
  3. Inadequate documentation
  4. All of the above

Answer(s): D



All of the following are examples of EUD, Except:

  1. Mainframe-based query tools
  2. Vendor packages that automate a generic business process
  3. Operating ystems s
  4. End-user developed applications

Answer(s): C



Which of the following is a risk associated with end-user computing:

  1. Weak security
  2. Inadequate support
  3. Inadequate training
  4. All of the above

Answer(s): D



Testing, which verifi es that the application can be implemented without interruption to business and that there is enough capacity is:

  1. Unit testing
  2. Functional testing
  3. Technical stintge
  4. Performance and load testing

Answer(s): D