Which of the following is NOT the element o0f a project plan?

  1. Objectives
  2. Contractual agreements
  3. Replenishment plan
  4. Resource requirements

Answer(s): C



A horizontal bar chart used in project management that is commonly used to plot the planned and actual progress of project activities is known as:

  1. Gantt chart
  2. Agreement chart
  3. Progression chart
  4. performance chart

Answer(s): A



A form of network diagram that graphically portray the sequential relationships and interdependence between the project tasks is called:

  1. Steps Forward Method
  2. Critical Path Method
  3. Evolutionary Method
  4. Development Method

Answer(s): B



Coding activities might include:

  1. Direct responsibility
  2. needs notification
  3. issues approval
  4. All of the above

Answer(s): D