What provides an illustration of the project's scope sand all tasks become the basic for monitoring the project's progress?

  1. Work breakdown structure
  2. Progress structure
  3. Project manual structure
  4. Process flow structure

Answer(s): A



Which of the following is NOT the element o0f a project plan?

  1. Objectives
  2. Contractual agreements
  3. Replenishment plan
  4. Resource requirements

Answer(s): C



A horizontal bar chart used in project management that is commonly used to plot the planned and actual progress of project activities is known as:

  1. Gantt chart
  2. Agreement chart
  3. Progression chart
  4. performance chart

Answer(s): A



A form of network diagram that graphically portray the sequential relationships and interdependence between the project tasks is called:

  1. Steps Forward Method
  2. Critical Path Method
  3. Evolutionary Method
  4. Development Method

Answer(s): B



Coding activities might include:

  1. Direct responsibility
  2. needs notification
  3. issues approval
  4. All of the above

Answer(s): D