A stakeholder in a project has been classified as having no interest but high power/influence on the power/interest grid.
Which of the following would be an appropriate way of managing this stakeholder?

  1. Ignore.
  2. Watch.
  3. Keep onside.
  4. Keep informed.

Answer(s): B



Which of the following is likely to be shown as a process in a swim-lane diagram of a library book borrowing system?

  1. Book.
  2. Librarian.
  3. Borrowing Limit.
  4. Borrow book.

Answer(s): D



The Business Activity Model shows the doing activities of a business system.
Which element of CATWOE do these activities relate to?

  1. Transformation.
  2. Actors.
  3. Environment.
  4. Owner.

Answer(s): A



Which of the following statements about change and change management is correct?

  1. Change management should be considered right from the start of the project.
  2. Change management should first be considered in the design stage of the project.
  3. The management of change is the sole responsibility of the project manager.
  4. Social and cultural factors have little influence on the success of implementing changes.

Answer(s): A