What is used by Managers for analyzing qualitative data such as competencies so they can align the right person for the right job?

  1. A Matrix
  2. Surveys
  3. Q & As
  4. Interviews

Answer(s): A



What is WBS?

  1. Watch Budget System
  2. Work Break-Down Structure
  3. Work Budget Software
  4. Win Bid System

Answer(s): B



A Project Manager learns that a raw material used in the Project is not the exact product that they ordered; and, is substandard. The Supplier is in foreign country and is difficult to contact.
What document types should be used in this activity?

  1. Yellow Pages; and, Legal Matrix
  2. Communication Plan; and, Legal Matrix
  3. Outlook Suppliers Group; and Issue Log Document
  4. Communication Plan; and Issue Log Document

Answer(s): D



During the Planning Phase, Project Director Syed needs to contact one of their largest customers but wastes 2 hours of valuable time locating the contact information. The Project Manager determines there are an extremely large number of Communication documents several concurrent Projects.
What should the Project Director implement to reduce the confusion?

  1. Master call list
  2. A Team Liaison Nominee
  3. Project Codification
  4. All of the above

Answer(s): D