UPS The front-end input can be two mains, one main and one standby, or one mains and one diesel engine input.

  1. True
  2. False

Answer(s): A



ABC Circuit breakers are mainly used IT Load front end, such as ups Inside the output cabinet.

  1. True
  2. False

Answer(s): B



One ups The capacity is 200KVA, Its output power factor is 0.9, Then it can drive at most ______________load.

  1. 180KW

Answer(s): A



The use of water fire and foam fire extinguishing systems in the data center will not cause damage to communication equipment.

  1. True
  2. False

Answer(s): B



The following _______________are not part of the chilled water air conditioner.

  1. condensants

Answer(s): A